Project 14

282 VICTORIA AVENUE, CHATSWOOD

Robotic Lift Shaft Penetrations

Project Details

Location

282 Victoria Avenue, Chatswood NSW

Project Type

Robotic lift shaft demolition

Duration

5 days (original estimate: 3 weeks)

Our Approach

Stripout Bros was contacted by a concrete cutting contractor to develop a methodology that could achieve 18 lift shaft penetrations across 6 levels within a 5-day window, ready for the lift installer to follow. The method already underway on site was tracking at roughly three weeks for the full scope. We crane-lifted a Husqvarna DXR 140 electric remote-controlled demolition robot level by level and worked from inside the completed lift shaft walls, removing approximately 4 lift shafts per day. By Friday of that week all 18 lift shafts were cut, demolished and cleared, on program and ready for the lift installer to move straight in.

18
Lift shaft penetrations
6
Levels
5 Days
Total execution time
3 Weeks
Original estimate

The Challenge

A three-week method and a five-day window

Stripout Bros was contacted by a concrete cutting contractor to develop a methodology that could achieve 18 lift shaft penetrations across 6 levels within a 5-day window, ready for the lift installer to follow.

The method already underway on site was to back-prop each lift shaft level by level, then cut and mechanically remove the concrete blocks after cutting. From day one it was clear this approach was unachievable inside the program. At that rate, completing all 18 lift shafts would have taken at least three weeks, putting the entire lift installation program at risk.

Scale
18 separate lift shaft penetrations required across 6 levels of the building.
Failing methodology
The level-by-level back-prop, cut and mechanically remove approach was tracking at roughly three weeks for the full scope.
Confined shaft environment
Works needed to be carried out inside lift shafts where the walls were already built, leaving very little room to move.
Critical-path program
The lift installer was scheduled to follow directly behind, so a 5-day turnaround was non-negotiable.
A view along a concrete lift shaft at Chatswood, with an opening at each level

The Method

Around four shafts a day, from inside the walls

From day one, Stripout Bros executed a methodology that allowed us to remove approximately 4 lift shafts per day, turning a three-week program into a 5-day delivery.

The equipment behind it was our specialised robotic fleet: a Husqvarna DXR 140, delivering hitting power comparable to a 5-tonne machine, small and nimble enough to be lifted level by level using the onsite crane and to work from inside the lift shafts where the walls were already built. Running fully electric, the DXR 140 gave us enormous breaking power for a very tight, confined location, without the fumes or ventilation issues a diesel machine would have created.

Crane-lifted, level by level
The robot was lifted to each level by the onsite crane rather than tramming through the building.
Compact enough to work inside the shaft
Small enough to operate within lift shaft walls that were already constructed.
5-tonne-class hitting power
Enough breaking force to cut through the program at pace, in a machine sized for the space.
100% electric
Zero exhaust emissions, critical in a confined vertical shaft environment.
Around-the-clock program
The team worked continuously through the week to hit the Friday deadline.
A Husqvarna demolition robot standing on its outriggers beside a concrete column at a lift shaft opening in Chatswood

The Solution

All 18 lift shafts, handed over by Friday

By Friday of that week, all 18 lift shafts were cut, demolished, and the resulting materials removed to the disposal areas allocated by the client.

The scope finished on program, ready for the lift installer to move straight in.

Program
5 days actual versus roughly 3 weeks under the original methodology, a critical-path program recovered.
Production
Approximately 4 lift shaft penetrations completed per day across 6 levels.
Environment
100% electric methodology, safely operated within confined, already-built lift shafts.
Client outcome
All 18 lift shafts cut, demolished and cleared to the client’s disposal areas, handed over ready for lift installation to begin.
A row of finished lift shaft openings in a concrete wall at Chatswood

Client Feedback

From day one the Stripout Bros team strategically created a methodology that had been unseen and unmatched in the industry. This sheer commitment to meeting our deadlines and working in a live environment, with the complications that this site presented, was no challenge. Started on Monday, completed on Friday; I have never seen a team this equipped in my entire career.

Project client, 282 Victoria Avenue, Chatswood

WHAT’S NEXT?

Our Latest Work

Explore how we sawed more than 100 linear metres of oversized retaining wall down to council-compliant heights in Padstow Heights.

READ MORE

Our Divisions

We’ve built Stripout Bros into a multi-division demolition and enabling works business so clients can rely on one team across critical early project scopes. Less overlap. More control. Better delivery.

READ MORE

WALL OPENINGS

STRIPOUT & DEMOLITION

ROBOTICS

CONCRETE CARE

WASTE MANAGEMENT

CONTACT

GET IN TOUCH

We’d love to hear about your next project. Whether it’s a wall opening, first enabling works, office floor, robotic work or full defit, send us your plans, photos or brief and Stripout Bros will come back with a clear scope and straight‑up quote.

Thanks — your enquiry is on its way. Stripout Bros will be in touch shortly.

OUR LATEST

Follow Us